Why deal term sheets should not be taken lightly

Apr 15, 2021

On February 15, 2021, an arbitral tribunal (the “Tribunal”) issued an award in a dispute between Zostel Hospitality Private Limited (“Zostel”) and Oravel Stays Private Limited (“Oyo”). The parties to the dispute operate accommodation management and booking business in India. In its award, the Tribunal held that a term sheet executed between Zostel and Oyo was binding in nature despite the express declaration in the preamble of the term sheet stating that it was non-binding and merely exploratory.

This update highlights the reasoning of the Tribunal and outlines the key takeaways which must be borne in mind by parties intending to execute deal term sheets in India.

The Dispute

Zostel and Oyo entered into a term sheet on November 25, 2015 (the “Term Sheet”) for the purpose of acquisition by Oyo of Zostel’s assets, including, its intellectual property rights, software, key employees, property data, and customer data.

The Term Sheet explicitly stated that it was not intended to be binding on the parties and provided that the closing of the proposed acquisition would be subject to fulfillment of the below-listed conditions:

• Oyo completing a limited legal and financial diligence of Zostel;

• Zostel obtaining all corporate, governmental, management, third party exchange control and the regulatory approvals that are necessary or advisable;

• The parties completing all other conditions identified in the annexure to the Term Sheet, including:

(i) mutual withdrawal of litigation initiated by the parties against each other;
(ii) transfer of all consumer traffic, including, calls, website queries, and application-based queries from Zostel to Oyo;
(iii) transfer of assets by Zostel to Oyo;
(iv) intimation by Zostel of the closure of its operations and its acquisition by Oyo to all stakeholders, including, property owners, customers, and employees;
(v) handover by Zostel of all customer and property-related data, records, and contracts to Oyo; and
(vi) execution of certain documents required by Oyo for the satisfaction of the employer/option holder liabilities.

The Term Sheet also stipulated that the parties would mutually agree upon and execute certain documentation for the purposes of the acquisition, including, the share subscription/merger framework agreement, the shareholders’ agreement, and the asset/business transfer agreement (collectively, the “Definitive Agreements”). The execution of the Term Sheet granted Oyo an opportunity to conduct due diligence on Zostel, and Zostel was obligated to provide all necessary information, documents, and materials.

Zostel alleged that it had completed all actions required to be taken by it under the Term Sheet and that Oyo’s acts and omissions had resulted in the breach of Oyo’s obligations under the Term Sheet to formally conclude the proposed acquisition. Given this, the dispute revolved around whether Oyo had deprived Zostel of the benefits envisioned under the Term Sheet and whether Zostel was entitled to claim specific performance of the Term Sheet in respect of the proposed acquisition.

Indian Law

Prior to the decision of the Tribunal, India’s Supreme Court has held on multiple occasions that a non-binding term sheet or letter of intent merely indicates a party’s intention to enter into a contract with the other party in the future. Further, the Supreme Court has held that a letter of intent is not intended to bind either party to ultimately enter into any contract. (Paragraph 34, Dresser Rand S.A. v. BINDAL Agro Chem Limited, AIR 2006 SC 871.)

India’s Supreme Court has also held that if the conditions stipulated in a non-binding letter of intent or term sheet are not fulfilled by a seller and if the conduct of the seller is otherwise not capable of generating confidence, the acquirer is entitled to withdraw the letter of intent. At this stage, there is no binding legal relationship between the acquirer and the seller, and the acquirer is entitled to look at the totality of the circumstances in deciding whether to enter into a binding contract with the seller. (Paragraph 7, Rajasthan Co-operative Dairy Federation Limited v. Shri Mahal Laxmi Mingrate Marketing Service Private Limited, AIR 1997 SC 66.)

Notwithstanding the foregoing, the Supreme Court has also cautioned prospective parties that an agreement can come into existence through correspondence if the correspondence unequivocally and clearly shows that the parties were ad idem on the terms. In this regard, a court must assess the actions of the parties and infer whether the intention expressed in the correspondence was to bring into existence a mutually binding contract. Given this, if the correspondence shows that there has been a meeting of minds between the parties and that they have actually reached an agreement on all material terms, it can be said that a binding contract is capable of being spelled out from the correspondence. (Rickmers Verwaltung GmbH v. Indian Oil Corporation Limited, AIR 1999 SC 504.)

Given the foregoing, it is clear that Indian courts have, in the past, not enforced an obligation to enter into an agreement by way of specific performance if the letter of intent or term sheet clarifies that it does not constitute a binding offer as a whole. At the same time, courts have held that both, the entirety of the term sheet and/or the letter of intent, and the conduct of the parties, must be analyzed to determine whether the parties intended to enter into a mutually binding agreement.

Order of the Tribunal

At the outset, the Tribunal stated that as a principle, it is required to consider the Term Sheet as a whole and that it could not draw conclusions merely by reading the preamble and ignoring the clauses which form the main subject matter of the Term Sheet. In the foregoing context, the Tribunal observed as follows:

  • The conditions mentioned in the Term Sheet required the parties to fulfill several obligations, including, withdrawal of litigation, transfer of consumer traffic and assets, and handover of data and records. These obligations were in the nature of closing obligations enabling the acquisition by Oyo, separate from any additional closing actions that would have been listed in the Definitive Agreements. Given this, the contents of the Term Sheet negated the contention that the Term Sheet was a non-binding and merely exploratory document.
  • The execution of the Term Sheet granted Oyo the right to conduct due diligence on Zostel’s business and provided Oyo with access to sensitive commercial information which would not have been shared by Zostel with a competitor in the ordinary course of its business. Given this, the Term Sheet could not be held to be non-binding in its entirety and gave rise to, at least, the binding obligation for Zostel to provide the necessary material, information and documents to Oyo.
  • Zostel satisfied all of the conditions mentioned in the Term Sheet which were within its power. These conditions included the transfer of its assets, consumer and vendor contracts, consumer and vendor data, and employees to Oyo. Oyo acknowledged the completion of the due diligence exercise to its satisfaction and provided a board resolution to Zostel confirming Oyo’s intent to complete the acquisition. While the parties did not withdraw the litigation against each other, the parties filed an application before the relevant forums stating that an “in-principle” agreement had been mutually reached by them. Lastly, the parties also agreed upon the form of the Definitive Agreements, except to the extent of the consideration which was subject to a formal valuation. Given the foregoing, from the facts of the matter, the only obstacle in the consummation of the transaction was certain additional demands made by one of Oyo’s shareholders, Venture Nursery. In this regard, Oyo had assured Zostel that it believed the demands to be unreasonable and intended to consummate the transaction by seeking a mutually acceptable solution or the exit of Venture Nursery. Due to this uncertainty, the parties were in discussions to revise the proposed structure of the transaction under the Definitive Agreements. Given this, the conduct of the parties pursuant to the execution of the Term Sheet suggested that the parties had agreed to complete the proposed acquisition.
  • The Term Sheet contained a framework for the acquisition, subject to which the parties were required to execute the Definitive Agreements. Further, the Term Sheet listed several conditions in the nature of key closing obligations. Given this, the fulfillment of the conditions and the conduct of the parties post the acquisition suggested that the parties waived the non-binding preamble of the Term Sheet and created a binding and enforceable contract.

On the basis of the foregoing, the Tribunal held that the Term Sheet was a binding contract between the parties. Nevertheless, the Tribunal also held that, as the parties had not identified a specific consideration and had not resolved certain structural issues, the parties could not be said to have consensus ad item in respect of the Definitive Agreements. Given this, while the Tribunal allowed Zostel to file proceedings praying for specific performance of the obligation to execute the Definitive Agreements, the Tribunal specifically refused to direct Oyo to pay any consideration, damages, or interest to Zostel at this stage.

Key Takeaways

While the Tribunal’s order has not yet been enforced, challenged, or analyzed by any courts in India, the order gives rise to certain key considerations which must be kept in mind by parties intending to enter into a non-binding term sheet or letter of intent in India. These include:

  • Parties should not rely on the mere use of the phrase, “non-binding” to determine the risk of their exposure. Instead, parties must ensure that the document as a whole implies the intention of the parties to not create any binding purchase obligations.
  • Parties should ensure that a non-binding term sheet or letter of intent does not include any obligations in the nature of definitive closing obligations or conditions that are typically completed as a part of the closing of a transaction.
  • Parties should be mindful of their conduct pursuant to the execution of a non-binding term sheet or letter of intent and should ensure that they do not take any actions which suggest a definite intention to complete the transaction.

About the Author

Amrit Mehta, Partner at Majmudar & Partners whose inputs were featured in the July 2018 edition of Asian Legal Business Magazine

Amrit Mehta has over 12 years of experience in corporate/M&A, insurance and real estate financing, and has advised on domestic and cross-border acquisitions, joint ventures, private equity investments, foreign direct investments and insurance matters.

Amrit has completed a 4 months’ secondment as a foreign lawyer at the Tokyo office of Mori Hamada and Matsumoto, a leading law firm in Japan in 2016. He spoke on “Current legal developments in M&A in Asia” at the International Bar Association’s Asia Pacific Mergers & Acquisitions Conference held in Tokyo in November 2019.

More Insights

Fact-check units: an unchecked fact checker – Part II

Download .pdf The Bombay High Court has recently struck down the 2023 amendment (the “2023 Amendment”) to the Information Technology (Intermediary Guidelines and Digital Media Ethics Code) Rules, 2021 (the “Intermediary Rules”), which amended Rule 3(1)(b)(v)...

read more

Failure to pay salary is not criminal conduct

Download .pdf Background The former Chief Executive Officer (the “Complainant”) of Safal Life Science (P) Ltd. (the “Company”) filed a criminal complaint under Sections 420 (cheating), 406 (criminal breach of trust), and 34 (acts done by several persons with common...

read more
Share This